Ads

Friday, March 6, 2015

Guidelines on use of Ready Mixed Concrete

GUIDELINES ON USE OF READY MIXED CONCRETE

1. Temperature of concrete:

Concrete is not recommended to be placed at a temperature above 40 oC
and below 5o C without proper precaution as laid down in IS: 7861 (Pt.I or
pt. II as the case may be ). IS:7861 pt. I deals with hot weather concreting
and Pt.II deals with cold weather concreting.

1.1 Hot weather concrete:

Any operation of concreting done at atmospheric temperature above 40 oC may be put under hot weather concreting. In the absence of special precautions as laid down under IS: 7861 (Pt.I), the effect of hot weather may be as follows:

a) Accelerated setting: A higher temperature of fresh concrete results in a more rapid hydration and leads to reduced work ability accelerated setting. This reduces the handling time of concrete.

b) Reduction in strength: Concrete mixed, placed and cured at higher temperature normally develops higher early strength than concrete produced and cured at normal temperature but at 28 days
or later the strength are generally lower.

c) Increased tendency to crack: Rapid evaporation may cause plastic shrinkage and cracking and subsequent cooling of hardened concrete would introduce tensile stresses.

In order to avoid harmful effect of hot weather concreting IS: 7861 (Pt.1) recommends that temperature of ingredients should be controlled so that the temperature of produced concrete is lower. Mixing water has the greatest effect on lowering of temperature of concrete. The use of chilled water/ flaked ice in mixing produces adequate reduction in concrete temperature.

In order to control the temperature of concrete and to avoid adverse effect of hot weather, it is desirable to limit the maximum temperature of concrete as 35 oC to keep margin for increase in temperature during transit.

1.2 Cold weather concreting:

Any concreting operation done at a temperature below 5 oC is termed as cold weather concreting. IS: 7861 (Pt.II) recommends special precautions to be taken during cold weather concreting.

In the absence of special precautions, the effect of cold weather concreting may be as follows:

a) Delayed setting:- When the temperature is falling to about 5oC or below, the development of strength of concrete is retarded compared with development at normal temperature. Thus, the
time period for removal of form work has to be increased.

b) Freezing of concrete at early stage:- The permanent damage may occur when the concrete in fresh stage is exposed to freeze before certain pre-hardening period. Concrete may suffer irreparable loss in its properties to an extant that compressive strength may get reduced to 50% of what could be expected for normal temperature concrete.

c) Stresses due to temperature differentials:- Large temperature differentials within the concrete member may promote cracking and affect its durability adversely.

In view of above, it is desirable to limit the lowest temperature of
concrete as 5o C

Jointed Plain Concrete Pavement

Jointed plain concrete pavement (JPCP, Figure 1) uses contraction joints to control cracking and does not use any reinforcing steel. Transverse joint spacing is selected such that temperature and moisture stresses do not produce intermediate cracking between joints. This typically results in a spacing no longer than about 6.1 m (20 ft.). Dowel bars are typically used at transverse joints to assist in load transferTie bars are typically used at longitudinal joints.


Properties

Crack Control

Contraction joints, both transverse and longitudinal

Joint Spacing

Typically between 3.7 m (12 ft.) and 6.1 m (20 ft.). Due to the nature of concrete, slabs longer than about 6.1 m (20 ft.) will usually crack in the middle. Depending upon environment and materials slabs shorter than this may also crack in the middle.

Reinforcing Steel

None.

Load Transfer

Aggregate interlock and dowel bars. For low-volume roads aggregate interlock is often adequate. However, high-volume roads generally require dowel bars in each transverse joint to prevent excessive faulting.

Other Info

A majority of U.S. State DOTs build JPCP because of its simplicity and proven performance.


- Source at: http://www.pavementinteractive.org/article/jointed-plain-concrete-pavement

Why dowel bar is provided in road pavement joints?

Dowel bars are short steel bars that provide a mechanical connection between slabs without restricting horizontal joint movement. They increase load transfer efficiency by allowing the leave slab to assume some of the load before the load is actually over it. This reduces joint deflection and stress in the approach and leave slabs.


Dowel bars are typically 32 to 38 mm (1.25 to 1.5 inches) in diameter, 460 mm (18 inches) long and spaced 305 mm (12 inches) apart but it depend on each country's standard code because it can be different from each other. Specific locations and numbers vary by state, however a typical arrangement might look like Figure 1. In order to prevent corrosion, dowel bars are either coated with stainless steel (Figure 2) or epoxy (Figure 3). Dowel bars are usually inserted at mid-slab depth and coated with a bond-breaking substance to prevent bonding to the PCC. Thus, the dowels help transfer load but allow adjacent slabs to expand and contract independent of one another. Figure 3 shows typical dowel bar locations at a transverse construction joint.

Figure 2. Stainless steel-clad dowel bars/ (Epoxy Coating on Ends Only)

Figure 3. Dowel bars in place at a construction joint- the green color is from the epoxy coating.
Source: http://www.pavementinteractive.org/article/dowel-bar/

Why reinforcement in road pavement?

Jointed reinforced concrete pavement (JRCP, see Figure 1) uses contraction joints and reinforcing steel to control cracking. Transverse joint spacing is longer than that for JPCP and typically ranges from about 7.6 m (25 ft.) to 15.2 m (50 ft.). Temperature and moisture stresses are expected to cause cracking between joints, hence reinforcing steel or a steel mesh is used to hold these cracks tightly together. Dowel bars are typically used at transverse joints to assist in load transfer while the reinforcing steel/wire mesh assists in load transfer across cracks.


Properties

Crack Control

Contraction joints as well as reinforcing steel.

Joint Spacing

Longer than JPCP and up to a maximum of about 15 m (50 ft.). Due to the nature of concrete, the longer slabs associated with JRCP will crack.

Reinforcing Steel

A minimal amount is included mid-slab to hold cracks tightly together. This can be in the form of deformed reinforcing bars or a thick wire mesh.

Load Transfer

Dowel bars and reinforcing steel. Dowel bars assist in load transfer across transverse joints while reinforcing steel assists in load transfer across mid-panel cracks.

Other Info

During construction of the interstate system, most agencies in the Eastern and Midwestern U.S. built JRCP. Today only a handful of agencies employ this design (ACPA, 2001[1]).
In general, JRCP has fallen out of favor because of inferior performance when compared to JPCP and CRCP.

Source: http://www.pavementinteractive.org/article/jointed-reinforced-concrete-pavement

Friday, January 2, 2015

Advanced Concrete Technology by Zongjin Li

http://www.mediafire.com/view/321g9jib8ly8ew5/Advanced_Concrete_Technology_by_Zongjin_Li(www.engineersdaily.com).pdf

Pressure grouting method statement


Pressure grouting is method of injecting specially formulated cement based mixes under pressure to improve strength or reduce permeability of concrete structures.Cement grouting is usually performed by drilling holes into application area to intercept open cracks, joints, fissures or cavities, then pumping under pressure balanced and stabilized grout mixes using a combination of cement, water, and additives.Pressure grouting method is widely adopted and it is very successful in solving leakage problems.
Materials used for pressure grouting
1.     Ordinary portland cement
2.     non shrink grout
3.     potable water
Tools and tackles used for pressure grouting
i) Air compressor with a capacity of 3 to 4 cum/ per minute and with a pressure of 3 to 5 kg per sq.cm.
ii) Grout injecting machine or grouting pump with inlet and outlet valves and pressure gauges. It should be capable of injecting cement grout up to 5 kg/cm2
iii) An air tight, pressure mixer chamber, with stirrer for proper mixing of the grout and keeping it in proper colloidal suspension during grouting.
iv) Flexible pressure hose pipes for transmitting grout from pressure chamber to ports embedded in the masonry.
v) Drilling equipment, pneumatic or electric, for drilling of holes upto 25mm dia.
vi) 10-20mm dia G.I. pipes with couplers, or lockable type PVC nozzles.

Driiling hole for nozel fixing

Pressure grouting

Pressure grouting tools


Pressure grouting procedure

1.     PVC grouting nozzles of 130mm length & 10mm outer dia, with a stopper at the outer end, shall be fixed on the concrete surface @ 1m C/C or at the particular location of water leakage, by drilling a hole of same dia and inserting upto a depth of 80mm. Cement paste shall be used to fix and seal the sides of the nozzle.
2.     After 24 hrs of fixing of nozzles, grouting operation shall be carried out.
3.     The Grout shall be prepared with mix of OPC & non shrink grouting chemical, W/C ratio shall be maintained not more than 0.45.
4.     Grout mix shall be prepared of good consistency for ease in passing through grouting pipe.
5.     The grouting shall be done under pressure of 3 to 5 kg/cm2 using grouting pump.
6.     Grout shall be pumped till the time it flows into the structure, filling all the gaps inside. The consumption of grout in each hole shall be recorded.
7.     Once completed and grout is completely set, the projected parts of the nozzles shall be removed, surface shall be cleaned and finished smooth.



Source: www.construction-guide.in/civil-works/plain-and-reinforced-concrete/pressure-grouting-procedure


Why waterproofing and How is the performance?






Regulation of construction permit

KINGDOM OF CAMBODIA
NATION    RELIGION    KING




REGULATION

Below is a detailed summary of the procedures, time and costs to build a warehouse in Cambodia. This includes obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections.
This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 189 economies. The most recent round of data collection was completed in June 2013.

No.
Procedure
Time to Complete
Associated Costs
1
Pick up application form


Agency: Municipal Department of Land Management, Construction and Urban Planning    
1 day
KHR 4,500
2
File documents with the Sangkat Office for review

According to Subdecree No.86 (dated December 19, 1997), relating to the construction permit, the documents attached to the official letter application must contain at least the following (10 copies on 21 x 29.7 cm. paper):
• Certificate to the estate or title certificate to the estate or the temporary occupation permit to the land
• Sheet of plot: this plan (title certificate to the land) shall be made by a private land surveyor or by the land office’s private agent
• Plan of warehouse location on the plot. This plan specifies the stationing of construction in the plot, the object of the application, by stating the following: the distance between one or more buildings and boundaries of the plot and the distance of the neighboring existing buildings; all arrangements of other sectors of the vacant land, with clarification on the type of land and existing crops and would-be car parks and fences; drainage pipes outside the building (substance, diameter, slope, height level, checking hole) up to the connection point of public network for draining sewage and for clean water, latrine, sink, and well; and stable point of the height of plot after the arrangement
• Plan of all warehouse floors (scale 1:100)
• Plan of the underground parts and latrine sinks (scale 1:100)
• Plan of front warehouse (scale 1:100)
• Plan of divided parts (scale 1:100). This plan shows the same as the front face plan, with one part showing the hygienic latrine sink
• Table of the surface area for each floor
• Technical specifications for calculating the ground level surface. Upon receiving the construction permit, BuildCo must prepare a detailed plan of the construction integration. The Ministry of Public Works and Transportation will review this plan before the construction site is opened

Procedures 1 to 5 take 30 days. The time frame for completing the permit approval process has been shortened. Under the relevant sub decree on construction permits, the time frame is fixed to at least 45 days to complete any project broader than more than 3,000 square meters.

There is no official fee; however, an informal fee must be paid to facilitate the application.

Agency: Sangkat Office
14 days
no charge
3
Request and obtain certification from the Khan or District Governor

According to the Decision No. 05 SSR dated February 6, 2006 from the Ministry of Land Management Urban Planning and Construction, this procedure must follow Procedure 2. The time frame should be 5 working days. The certification fee is not provided for by law. If informal fees are not paid, it generally takes between 4 months to a year to obtain the certification.
Agency: Khan/ District Governor
182 days
no charge
4
File documents to the Khan Land Management, Urban Planning, and Construction Office for review, and obtain approval

The following documents must be submitted within 6 days after Procedure 2 has been completed:
• Plot plan
- Structural and engineering plans
• Plan of the location of the warehouse on the plot
• Plan of all warehouse floors. This plan specifies the purpose of using the rooms and the area, sanitation installation, and areas for pipes placing
• Plan of the underground parts and the latrine sinks (scale, 1:100)
• Plan of front building (scale 1:100): This plan specifies the front face plan, showing the height level of the following: each floor; land at the bottom of the building, by specifying the height level of natural land, filled land, or removal land; the roof and limit of roof or height of existing terrace and the wall barriers; existing flower's pole and substance for front face
• Plan of divided parts (scale, 1:100): This plan shows the same as the front face plan with one part showing the hygienic latrine sink
• Table of surface area for each floor
• Technical specifications for calculating the ground level surface
• Additional documents: the applicant may be requested to provide additional documents for reasons of hydrology, prevention against all types of annoyance, public order, and protection of patrimony or landscape
• Title certificate
• Application for construction permit (10 copies)

There is no official fee; however, an informal fee must be paid.

Agency: Khan Land Management, Urban Planning, and Construction Office
14 days
no charge
5
Request and obtain the approval (building permit) of the Municipality/Ministry of Land Management Urban Planning and Construction

BuildCo must file the documents with the Sangkat/Commune first (to Khan/District), then with (a) the Municipality/ Province for plots under 3,000 sq. m. or (b) the Ministry of Land Management, Urban Planning and Construction for plots above 3,000 sq. m. However, BuildCo does not need to visit each government office if the builder hires an agent who handles the construction permit application to completion.

Fee schedule for construction permit:
• Surface of the construction on the land (SCL) less than or equal to 100 sq. m.: KHR 140,000.00
• Less than or equal to 200.00 sq. m.: KHR 160,000.00
• Less than or equal to 300.00 sq. M.: KHR 180,000.00
• Less than or equal to 400.00 sq. m.: KHR 200,000.00
• Less than or equal to 500.00 sq. m.: KHR 220,000.00
• Less than or equal to 1,000.00 sq. m.: KHR 260,000.00
• Less than or equal to 2,000.00 sq. m.: KHR 300,000.00
• Less than or equal to 3,000.00 sq. m.: KHR 340,000.00

Total building permit fee is about USD 6,000.00 to USD 7,000.00 (mainly a negotiable facilitation fee).

Based on the Decision No. 5 SSR from the Ministry of Land Management Urban Planning and Construction after the examination by the Khan Land office, the documents will be forwarded to the Phnom Penh Municipal Department of Land Management Urban Planning and Construction and Cadastre (the "PP LO"). At the PP LO, the documents will be examined by relevant office such as the Cadastral Office, Technical and Geography Office, Construction Office, Land management office. After the approval of the PP LO, the documents will be forwarded to the Phnom Penh Municipality (the "PPM") for last examination and issuance of Construction Permit to the applicant. The PPM shall have only 5 days to complete the review and issue the Construction Permit to the applicant. The construction permit is valid one year from the date of its issuance by the PPM and can be extended once for another year.

The Sub Decree No. 86 on construction Permit, in its Article 9.10 stipulates that, after obtaining the Construction Permit, there shall be an iron structure plan which will be examined by the Ministry of Public work and Transport. However, this is not enforced in practice, but maybe arbitrarily used by some officials.

Agency: Sangkat/ Commune and Municipality / Provincial Authority
365 days
no charge
6
Notify the Sangkat authority of obtainment of building permit

Under Cambodian regulation, after receiving the building permit from the provincial or municipal authority, the company must notify the other relevant authorities. Construction work must start within a year from the date of issuance of the construction permit.
Agency: Sangkat Office
1 day
no charge
7
Notify the Khan authority of obtainment of building permit

The Khan authority is notified about the building permit.
Agency: Khan Office/ District
1 day
no charge
8
Request official opening of the construction from the Phnom Penh Municipal Department of Land Management Urban Planning and Construction and Cadastre (the "PP LO")

BuildCo must inform the authorities about the start of the construction within 7 days. Then the authority will issue a declaration of "construction site opening". In order to start the construction and as required by Sub Decree No. 86 on Construction Permit and the decision No. 05, the construction owner shall apply to the PP LO (not the Khan Land Office or the Sala Khan) for an approval to open the construction site. The PP LO will respond to the request within 6 days.
Agency: Phnom Penh Municipal Department of Land Management Urban Planning and Construction and Cadastre (the "PP LO")
1 day
KHR 300,000
9
Receive an inspection from technical official

The Technical Department sends an expert to inspect the construction site before the construction starts.
Agency: Technical Department
1 day
no charge
10
Inform the building authority of the poles setup and receive inspection

The inspector may visit the site without notifying BuildCo. The inspection takes a few hours, depending on the construction size and complexity. After receiving notification from BuildCo, an inspector will visit the site within 2 or 3 days. It is not necessary to stop the construction work.
Agency: Technical Department
1 day
no charge
11
Inform the building authority after foundation work and receive inspection


Agency: Technical Department
1 day
no charge
12
Inform the building authority when columns are built and receive inspection


Agency: Technical Department
1 day
no charge
13
Inform the building authority when walls are erected and receive inspection


Agency: Technical Department
1 day
no charge
14
Inform the building authority when floors are built and receive inspection


Agency: Technical Department
1 day
no charge
15
Inform the building authority of the end of main works


Agency: Technical Department
1 day
no charge
16
Receive final inspection by the building authorities and departments concerned that issue the certificate of compliance

At the end of construction, the district or khan office and the construction permit office (urbanization and construction office) may check, simultaneously, that the erected building complies with the construction permit specifications. The municipal or provincial authority issues the certificate of compliance or could take legal action for noncompliance.

Agency: Khan Office/ District, Urbanization & Construction Office, Municipality/ Provincial Authority
21 days
no charge
Request and receive connection to water and sewage services

BuildCo must fill out some application forms for water and sewage connection.

BuildCo is not required to prepay government and service fees before, or at the time of, the connection. Instead, it must pay the following only after approval: the government fee [as listed below), the plumbing service fee (between KHR 200,000.00 (USD 50.00) and KHR 300,000.00 (USD 75.00) plus KHR 457,750.00 (USD 114.44)], and the water meter network length connection [plus KHR 92,800.00 (USD 23.20: water subscription cost)] = KHR 800,550.00.

The water subscription fee for networks varies by water connection type (Point A and Point B) and is based on network length and water-meter size:

Point A: Water subscription for new network is calculated as follows (for a network length of 15 mm):
• 0 to 10 mm: KHR 457,750.00 (USD 114.44)
• 11 mm to 20 mm: KHR 460,400.00 (USD 115.10)
• 21 mm to 30 mm: KHR 665,200.00 (USD 166.30)
• 31mm to 40 mm: KHR 772,250.00 (USD 193.06)
• 41 mm up to 50 mm: KHR 878,500.00 (USD 219.62)

Point B: Water subscription for available network with meter is calculated as follows (SN meter size water subscription fee):
• 15 mm: KHR 92,800.00 (USD 23.20)
• 20 mm: KHR 98,900.00 (USD 24.73)
• 25 mm: KHR 106,900.00 (USD 26.73)
• 30 mm: KHR 225,000.00 (USD 56.25)
• 40 mm: KHR 271,000.00 (USD 67.75)

Agency: Phnom Penh Water supply Authority (PPWSA)
42 days
KHR 800,550
* 18
Request and receive connection to telephone

To obtain a telephone connection, BuildCo submits an application and documentation. The telephone service provider does not conduct an on-site inspection before issuing the approval, but checks the cable system around the construction site. Payment must be made in full (for all services) after an agreement is reached between BuildCo and the service provider.
Agency: Telecom Cambodia
6 days
KHR 190,000
19
Inform the building authorities of the utilities setup

Although it is not stipulated in the law, it happens in practice.
Agency: Khan Office/ District
1 day
no charge
20
Receive inspection by building authorities

The building authorities inspect the construction site for compliance with the approved plan.
Agency: Khan Office/ District
1 day
no charge
* 21
Receive inspection by water authorities

In general, water and power supply companies must conduct on-site inspections to determine how to connect the construction to the network and to estimate the cost of this connection. In addition to providing water services, the utilities must ensure the connection is made according to the approved plan.
Agency: Phnom Penh Water Supply Authority (PPWSA)