Pressure grouting is method of injecting
specially formulated cement based mixes under pressure to improve strength or
reduce permeability of concrete structures.Cement grouting is usually
performed by drilling holes into application area to intercept open cracks,
joints, fissures or cavities, then pumping under pressure balanced and
stabilized grout mixes using a combination of cement, water, and
additives.Pressure grouting method is widely adopted and it is very successful
in solving leakage problems.
Materials
used for pressure grouting
1.
Ordinary portland cement
2.
non shrink grout
3.
potable water
Tools
and tackles used for pressure grouting
i)
Air compressor with a capacity of 3 to 4 cum/ per minute and with a pressure of
3 to 5 kg per sq.cm.
ii) Grout injecting machine or grouting pump with inlet and outlet valves and pressure gauges. It should be capable of injecting cement grout up to 5 kg/cm2
iii) An air tight, pressure mixer chamber, with stirrer for proper mixing of the grout and keeping it in proper colloidal suspension during grouting.
iv) Flexible pressure hose pipes for transmitting grout from pressure chamber to ports embedded in the masonry.
v) Drilling equipment, pneumatic or electric, for drilling of holes upto 25mm dia.
vi) 10-20mm dia G.I. pipes with couplers, or lockable type PVC nozzles.
ii) Grout injecting machine or grouting pump with inlet and outlet valves and pressure gauges. It should be capable of injecting cement grout up to 5 kg/cm2
iii) An air tight, pressure mixer chamber, with stirrer for proper mixing of the grout and keeping it in proper colloidal suspension during grouting.
iv) Flexible pressure hose pipes for transmitting grout from pressure chamber to ports embedded in the masonry.
v) Drilling equipment, pneumatic or electric, for drilling of holes upto 25mm dia.
vi) 10-20mm dia G.I. pipes with couplers, or lockable type PVC nozzles.
Driiling hole for nozel fixing
Pressure grouting
Pressure grouting tools
Pressure
grouting procedure
1.
PVC grouting nozzles of 130mm length &
10mm outer dia, with a stopper at the outer end, shall be fixed on the concrete
surface @ 1m C/C or at the particular location of water leakage, by drilling a
hole of same dia and inserting upto a depth of 80mm. Cement paste shall be used
to fix and seal the sides of the nozzle.
2.
After 24 hrs of fixing of nozzles,
grouting operation shall be carried out.
3.
The Grout shall be prepared with mix of
OPC & non shrink grouting chemical, W/C ratio shall be maintained not more
than 0.45.
4.
Grout mix shall be prepared of good
consistency for ease in passing through grouting pipe.
5.
The grouting shall be done under pressure
of 3 to 5 kg/cm2 using grouting pump.
6.
Grout shall be pumped till the time it
flows into the structure, filling all the gaps inside. The consumption of grout
in each hole shall be recorded.
7.
Once completed and grout is completely
set, the projected parts of the nozzles shall be removed, surface shall be
cleaned and finished smooth.



Valuable information you have shared
ReplyDeleteFor information on grouting chemicals visit : Roff.in
Thanks for u r information bro..
ReplyDeleteThanks for ur valuable post. It's very useful to us.
ReplyDeleteMaybe you will also be interested in this information
grouting machine
pressure grouting machine
cement grouting machine
hand pressure grout pump
injection packer
You can also use this to understand us
about us
I like your article so much !
ReplyDeletePlease visit our website to get more informations.
Hope it will be helpful for you!
Saking
has an unshakable commitment to becoming the leader in leak-proofing products
Grouting machine-
The professional model with structural perfusion, high pressure model, can solve the inconvenience of the builder carrying heavy machinery.
Hello, you can also refer to our company's products, which may be helpful to you
ReplyDeleteI'm coming!!!We are committed to reducing plastic garbage.
I strongly recommend this business
plastic recycling machine
Sheet Making Machine
Geording Machinery
we are actively expanding our business at home and abroad in order to gain a larger market share and to provide better service.
ReplyDeleteMy product:
dehumidifying dryer
mould temperature controller
industrial water chiller
material conveying system
vacuum conveyor
gravimetric blender
W/C ratio shall be maintained not more than 0.45.