Ads

Friday, March 6, 2015

Guidelines on use of Ready Mixed Concrete

GUIDELINES ON USE OF READY MIXED CONCRETE

1. Temperature of concrete:

Concrete is not recommended to be placed at a temperature above 40 oC
and below 5o C without proper precaution as laid down in IS: 7861 (Pt.I or
pt. II as the case may be ). IS:7861 pt. I deals with hot weather concreting
and Pt.II deals with cold weather concreting.

1.1 Hot weather concrete:

Any operation of concreting done at atmospheric temperature above 40 oC may be put under hot weather concreting. In the absence of special precautions as laid down under IS: 7861 (Pt.I), the effect of hot weather may be as follows:

a) Accelerated setting: A higher temperature of fresh concrete results in a more rapid hydration and leads to reduced work ability accelerated setting. This reduces the handling time of concrete.

b) Reduction in strength: Concrete mixed, placed and cured at higher temperature normally develops higher early strength than concrete produced and cured at normal temperature but at 28 days
or later the strength are generally lower.

c) Increased tendency to crack: Rapid evaporation may cause plastic shrinkage and cracking and subsequent cooling of hardened concrete would introduce tensile stresses.

In order to avoid harmful effect of hot weather concreting IS: 7861 (Pt.1) recommends that temperature of ingredients should be controlled so that the temperature of produced concrete is lower. Mixing water has the greatest effect on lowering of temperature of concrete. The use of chilled water/ flaked ice in mixing produces adequate reduction in concrete temperature.

In order to control the temperature of concrete and to avoid adverse effect of hot weather, it is desirable to limit the maximum temperature of concrete as 35 oC to keep margin for increase in temperature during transit.

1.2 Cold weather concreting:

Any concreting operation done at a temperature below 5 oC is termed as cold weather concreting. IS: 7861 (Pt.II) recommends special precautions to be taken during cold weather concreting.

In the absence of special precautions, the effect of cold weather concreting may be as follows:

a) Delayed setting:- When the temperature is falling to about 5oC or below, the development of strength of concrete is retarded compared with development at normal temperature. Thus, the
time period for removal of form work has to be increased.

b) Freezing of concrete at early stage:- The permanent damage may occur when the concrete in fresh stage is exposed to freeze before certain pre-hardening period. Concrete may suffer irreparable loss in its properties to an extant that compressive strength may get reduced to 50% of what could be expected for normal temperature concrete.

c) Stresses due to temperature differentials:- Large temperature differentials within the concrete member may promote cracking and affect its durability adversely.

In view of above, it is desirable to limit the lowest temperature of
concrete as 5o C

Jointed Plain Concrete Pavement

Jointed plain concrete pavement (JPCP, Figure 1) uses contraction joints to control cracking and does not use any reinforcing steel. Transverse joint spacing is selected such that temperature and moisture stresses do not produce intermediate cracking between joints. This typically results in a spacing no longer than about 6.1 m (20 ft.). Dowel bars are typically used at transverse joints to assist in load transferTie bars are typically used at longitudinal joints.


Properties

Crack Control

Contraction joints, both transverse and longitudinal

Joint Spacing

Typically between 3.7 m (12 ft.) and 6.1 m (20 ft.). Due to the nature of concrete, slabs longer than about 6.1 m (20 ft.) will usually crack in the middle. Depending upon environment and materials slabs shorter than this may also crack in the middle.

Reinforcing Steel

None.

Load Transfer

Aggregate interlock and dowel bars. For low-volume roads aggregate interlock is often adequate. However, high-volume roads generally require dowel bars in each transverse joint to prevent excessive faulting.

Other Info

A majority of U.S. State DOTs build JPCP because of its simplicity and proven performance.


- Source at: http://www.pavementinteractive.org/article/jointed-plain-concrete-pavement

Why dowel bar is provided in road pavement joints?

Dowel bars are short steel bars that provide a mechanical connection between slabs without restricting horizontal joint movement. They increase load transfer efficiency by allowing the leave slab to assume some of the load before the load is actually over it. This reduces joint deflection and stress in the approach and leave slabs.


Dowel bars are typically 32 to 38 mm (1.25 to 1.5 inches) in diameter, 460 mm (18 inches) long and spaced 305 mm (12 inches) apart but it depend on each country's standard code because it can be different from each other. Specific locations and numbers vary by state, however a typical arrangement might look like Figure 1. In order to prevent corrosion, dowel bars are either coated with stainless steel (Figure 2) or epoxy (Figure 3). Dowel bars are usually inserted at mid-slab depth and coated with a bond-breaking substance to prevent bonding to the PCC. Thus, the dowels help transfer load but allow adjacent slabs to expand and contract independent of one another. Figure 3 shows typical dowel bar locations at a transverse construction joint.

Figure 2. Stainless steel-clad dowel bars/ (Epoxy Coating on Ends Only)

Figure 3. Dowel bars in place at a construction joint- the green color is from the epoxy coating.
Source: http://www.pavementinteractive.org/article/dowel-bar/

Why reinforcement in road pavement?

Jointed reinforced concrete pavement (JRCP, see Figure 1) uses contraction joints and reinforcing steel to control cracking. Transverse joint spacing is longer than that for JPCP and typically ranges from about 7.6 m (25 ft.) to 15.2 m (50 ft.). Temperature and moisture stresses are expected to cause cracking between joints, hence reinforcing steel or a steel mesh is used to hold these cracks tightly together. Dowel bars are typically used at transverse joints to assist in load transfer while the reinforcing steel/wire mesh assists in load transfer across cracks.


Properties

Crack Control

Contraction joints as well as reinforcing steel.

Joint Spacing

Longer than JPCP and up to a maximum of about 15 m (50 ft.). Due to the nature of concrete, the longer slabs associated with JRCP will crack.

Reinforcing Steel

A minimal amount is included mid-slab to hold cracks tightly together. This can be in the form of deformed reinforcing bars or a thick wire mesh.

Load Transfer

Dowel bars and reinforcing steel. Dowel bars assist in load transfer across transverse joints while reinforcing steel assists in load transfer across mid-panel cracks.

Other Info

During construction of the interstate system, most agencies in the Eastern and Midwestern U.S. built JRCP. Today only a handful of agencies employ this design (ACPA, 2001[1]).
In general, JRCP has fallen out of favor because of inferior performance when compared to JPCP and CRCP.

Source: http://www.pavementinteractive.org/article/jointed-reinforced-concrete-pavement

Friday, January 2, 2015

Advanced Concrete Technology by Zongjin Li

http://www.mediafire.com/view/321g9jib8ly8ew5/Advanced_Concrete_Technology_by_Zongjin_Li(www.engineersdaily.com).pdf

Pressure grouting method statement


Pressure grouting is method of injecting specially formulated cement based mixes under pressure to improve strength or reduce permeability of concrete structures.Cement grouting is usually performed by drilling holes into application area to intercept open cracks, joints, fissures or cavities, then pumping under pressure balanced and stabilized grout mixes using a combination of cement, water, and additives.Pressure grouting method is widely adopted and it is very successful in solving leakage problems.
Materials used for pressure grouting
1.     Ordinary portland cement
2.     non shrink grout
3.     potable water
Tools and tackles used for pressure grouting
i) Air compressor with a capacity of 3 to 4 cum/ per minute and with a pressure of 3 to 5 kg per sq.cm.
ii) Grout injecting machine or grouting pump with inlet and outlet valves and pressure gauges. It should be capable of injecting cement grout up to 5 kg/cm2
iii) An air tight, pressure mixer chamber, with stirrer for proper mixing of the grout and keeping it in proper colloidal suspension during grouting.
iv) Flexible pressure hose pipes for transmitting grout from pressure chamber to ports embedded in the masonry.
v) Drilling equipment, pneumatic or electric, for drilling of holes upto 25mm dia.
vi) 10-20mm dia G.I. pipes with couplers, or lockable type PVC nozzles.

Driiling hole for nozel fixing

Pressure grouting

Pressure grouting tools


Pressure grouting procedure

1.     PVC grouting nozzles of 130mm length & 10mm outer dia, with a stopper at the outer end, shall be fixed on the concrete surface @ 1m C/C or at the particular location of water leakage, by drilling a hole of same dia and inserting upto a depth of 80mm. Cement paste shall be used to fix and seal the sides of the nozzle.
2.     After 24 hrs of fixing of nozzles, grouting operation shall be carried out.
3.     The Grout shall be prepared with mix of OPC & non shrink grouting chemical, W/C ratio shall be maintained not more than 0.45.
4.     Grout mix shall be prepared of good consistency for ease in passing through grouting pipe.
5.     The grouting shall be done under pressure of 3 to 5 kg/cm2 using grouting pump.
6.     Grout shall be pumped till the time it flows into the structure, filling all the gaps inside. The consumption of grout in each hole shall be recorded.
7.     Once completed and grout is completely set, the projected parts of the nozzles shall be removed, surface shall be cleaned and finished smooth.



Source: www.construction-guide.in/civil-works/plain-and-reinforced-concrete/pressure-grouting-procedure


Why waterproofing and How is the performance?